Inside the refinery fight against furnace coke: chemicals, coatings, and faster decokes

beta-pramesti-asiaindustry-refineryprocess-cracking

Inside the refinery fight against furnace coke: chemicals, coatings, and faster decokes

Cracking furnaces choke on coke. This carbon crust spikes pressure drop and metal temperatures, and it forces costly shutdowns. A layered playbook of anti-coking additives, smarter metallurgy and faster decoking has shown 2–4× longer runs and cleaner tubes.

Industry: Refinery | Process: Cracking

Call it the paradox of cracking. You push hydrocarbons hard enough to make value, and you risk laying down solid carbon. Coke (solid carbon deposits) forms on the inner surfaces of cracking furnace coils when long-chain hydrocarbons crack and polymerize. The rate of coke deposition depends strongly on feed quality (aromatics, sulfur content, metal contaminants) and coil metallurgy (researchgate.net) (pubs.acs.org).

In practice, fouling can limit run lengths to a few weeks or less. Heavy coke buildup raises coil pressure drop and furnace metal temperatures. Therefore the furnace has to be shut down for cleaning. Corrosion-resistant alloys or anti-coking coatings can cut the coke rate by a large amount. One study found more than 10× differences in coking rate between alloys (pubs.acs.org). In fixed-tube steam crackers, coke completely insulates the tube. Therefore operators shut down for decoking when the pressure drop or the skin temperature limit is reached. Preventing coke, and removing it efficiently when it forms, is important for keeping the unit available.

Chemical anti‑coking additives (definitions and dosing)

Refineries usually inject specialty chemicals ("anti-foulants") into the cracking feed at low concentrations (tens to hundreds of ppm) to inhibit coke. These additives combine passivators with radical scavengers. Passivators are compounds that form a thin metal oxide layer on the tube surface and block the catalytic sites for polymerization. Radical scavengers are molecules that react with radical intermediates in the gas phase and prevent long-chain formation. An Arkema patent describes injecting dimethyl sulfide/disulfide (DMS/DMDS) along with an aromatic radical scavenger (α-methylstyrene dimer, terpinolene or thiophene) at ~100–300 ppm each in the feed (patents.google.com) (patents.google.com). Typical dosing is on the order of 10–1000 ppm of each component. Most fields use ~50–500 ppm total (patents.google.com).

Field trials have shown large benefits. In a commercial ethylene furnace study, we added about 5–20 ppm of a proprietary inorganic salt blend (with water). Run length tripled: the heater operated about 150 days with the additive and only about 40 days without it (ogj.com). During 180 days with the additive, coil pressure drop stayed flat and ethylene/propylene yields were about 2% higher (ogj.com). Analysis showed about 20–30% higher CO₂ production in the flue gas. This indicates the additive was actively gasifying deposited coke as it formed (ogj.com). In another run, heavy tar (condensable side‑products) increased, so the recovered steam from transfer‑line exchangers rose about 30% because fouling was slower (ogj.com).

Additives at tens of ppm slowed coke formation by 2–4× and extended run lengths by factors of 3–4. They even activated partial on‑stream gasification. All of this had negligible impact on product quality (ogj.com) (ogj.com) (ogj.com). Common commercial anti‑coking formulations include sulfurized oils or salt mixtures. Examples cited are Nalco’s “COKE‑LESS” and Chevron‑Phillips’ “CCA‑500” (researchgate.net). Operators monitor coil pressure drop and add more chemical as needed to hold fouling in check. Additives usually end up in bottom oils, so the environmental impact is described as minor. One field trial reported that added coke (and chemicals) reported entirely to the tar oil and was later burned or used for carbon black, with no effluent issues (ogj.com) (ogj.com). Dosing at these low levels makes accurate chemical metering central to operations (for example, via a dosing pump).

Coil material and coatings (preventative measures)

Selected coil materials or coatings can greatly reduce coke. Alloys or ceramic coatings form stable oxide layers that stop coke sticking. AlcroPlex (an alumina‑based coating) doubled furnace run lengths in one ethane‑cracking test (30→60 days) (pubs.acs.org). A spinel‑coated alloy (Kubota ANK 400) extended three commercial furnaces from ~33 days to >400 days between decokes (pubs.acs.org).

These treatments reduce catalytic coke growth and carburization. Good metallurgy plus feed additives gives the best result. Slurry feeds or heavy naphtha cracked in coated coils still ran far longer than uncoated tubes. The choice of alloy or coating depends on cost. High‑chrome or silicon‑carbide materials raise capex. However, they allow much longer cycles and can run at much higher conditions (pubs.acs.org) (pubs.acs.org).

Steam–air decoking procedure (process steps)

Coke does build up, and it is usually removed by a controlled steam/air burn. The furnace is taken offline and each coil pass is isolated. A dedicated decoking system routes medium‑pressure steam and air into the coil, and vents the tube effluent to a quench pot. Operators usually inject steam only into the cool coil while the burner fires from outside. This creates thermal shock: the sudden heating and contraction cracks the coke layer (1library.net). The steam flow then sweeps most of the loose coke fragments into the decoke drum, where spray water quenches them. When the effluent runs clear, a small flow of air is added, usually premixed with steam or after a steam purge, and the flame is re‑ignited. The oxygen burns the remaining coke in‑place. A rise in coil metal temperature and in CO/CO₂ in the exhaust shows this is happening (1library.net) (cokebusters.com).

We control the process to avoid hotspots and mechanical stress. We clean only one pass at a time and monitor the tube metal temperature. We apply steam to the passes that are not being decoked so they do not dry out (scribd.com) (scribd.com). Steam–air decoking usually takes 1–2 days per heater, depending on the fouling. Textbook procedures give about 0.7 kg/cm² ΔP per 100 ft of coil when steaming, as a guide (scribd.com). Total decoke times can range from about 6 h for light fouling to 1–3 days for heavy coke (scribd.com).

There are drawbacks. The steam burn releases CO–CO₂–H₂ into the stack (cokebusters.com), so many plants collect the off‑gases and send them to flare or treat them. The procedures put safety first. For example, the coil is opened to air only after a thorough steam flush, so there is no explosive mixture. Crew costs are high. Usually 1–2 dedicated operators must attend the decoke continuously.

Other decoking methods (offline pigging, spalling, chemical)

Mechanical “pigging” (a dense piston with metal bristles pumped through the coil) has become a preferred alternative in many refineries. It removes nearly 100% of internal fouling and recovers almost the full heat‑transfer area (cokebusters.com). One refiner reported pigging two vacuum‑heater coils in 36 h and 24 h (two runs). The equivalent steam decoke needed 96+ hours (heatflux.com). Another removed the coke from a 4‑pass furnace in 18 h per pass. Steam took about 96 h (heatflux.com) (heatflux.com).

After pigging, heat transfer matched steam decokes, within measurement error (heatflux.com) (heatflux.com). Emissions are negligible because pigging is a closed, pumped process. Plant personnel can focus on other tasks, because steam decokes usually tie up operators for days (heatflux.com) (cokebusters.com). The downsides are the equipment cost and the need to track pigs carefully. One refinery noted that lost pigs have been found lodged after the process. Therefore inventory control is important (heatflux.com).

In-line spalling (on-stream pulsed steam) uses high-velocity steam bursts to cause rapid heating-cooling “shocks”. These shocks can dislodge some coke without a shutdown. In practice it gives only a partial cleaning (mostly in the radiant section) and is not a full substitute for off-line decokes (cokebusters.com). Chemical cleaning (circulating solvents or acids) is usually avoided in cracking heaters because it is slow, complex, and produces hazardous waste. For example, an acid wash might dissolve coke. However, it then leaves the coils corroded and needs neutralization.

Performance outcomes and trends (run length and yields)

The data show large gains from better decoking methods. In one industry survey, pigging cut heater downtime by 60–80% compared to steam burns (heatflux.com) (heatflux.com). Some refineries report 2–3× run‑length extensions. A crude visbreaker heater in Europe went from ~5‑day steaming cycles to ~2‑day pigging cycles, with equal heat recovery (heatflux.com). Fuel consumption dropped ~1.8% because the tubes were cleaner (heatflux.com).

In ethylene units, additives plus coatings let furnaces run safely well over 100 days between decokes. In the AlcroPlex case, runs doubled to 60 days (pubs.acs.org). Modern working alloys like ANK 400 claim cycles of more than 400 days (pubs.acs.org). The key metrics: aftermarket anti-foulant dosing (about 100–300 ppm) gives a measurable payback. Published trials showed ethylene yield rising by about 2% and furnace duty (steam keyed off) rising by about 2–3% under additive treatment (ogj.com) (ogj.com).

Longer runs mean less maintenance cost and more throughput. The field trial above achieved runs 3–4× longer (ogj.com). The ROI of pigging is just as clear. One operator noted that avoiding a 96-h steam burn (3–4 shift crews) in favour of a 36-h pigging saved essentially 3 shifts of labour and avoided noise and emissions issues (heatflux.com).

Regulatory and operations context (emissions and safety)

Most decoking emissions are CO and CO₂. They are flammable, but flares or scrubbers usually handle them. Cracking plants still need to comply with local air permits. For example, Indonesian refinery regulations need control of any CO, NOx or particulate emissions during maintenance. Steam burns can be reduced by pigging or partial on-stream decoke, and this helps cut the flaring. Care is also taken so that quench drums are not flooded with petroleum contaminants.

Recommendations (layered approach)

The practical playbook has several layers. First, keep coking precursor levels low with good feed purification (dry, low‑metal feeds) and optimized steam dilution. Second, keep coatings or high‑alloy tubes on heaters that foul heavily. Third, inject anti-foulant additives continuously or on a demand basis (10–500 ppm) to suppress coke. Fourth, plan decokes in advance: schedule pigging over steam‑air burns when possible, to cut downtime. With these measures, operators usually see large run‑length gains (2–4×) and can extend furnace campaigns to several months with little coke accumulation.

Source notes and citations

Researchgate.net and pubs.acs.org document the cause and impact of coke formation, the effect of alloy and coating, and the differences in run length (researchgate.net) (pubs.acs.org) (pubs.acs.org) (pubs.acs.org). Patents give the additive chemistry, the dosing ranges (10–1000 ppm each, ~50–500 ppm total typical) and the specific components (DMS/DMDS with α‑methylstyrene dimer, terpinolene or thiophene at ~100–300 ppm each) (patents.google.com) (patents.google.com). Field performance is reported by ogj.com and researchgate.net. Run length tripled to ~150 vs ~40 days, ethylene/propylene yields were ~2% higher, CO₂ in flue was ~20–30% higher, recovered steam from TLE was up ~30%, coke formation was 2–4× slower and runs were 3–4× longer. The environmental note says additives reported to tar oil were later burned or used for carbon black, and the additive has “neither acidic nor basic characteristics” (ogj.com) (ogj.com) (ogj.com) (ogj.com) (researchgate.net).

Steam–air decoking steps, controls and timeframes are detailed in 1library.net, scribd.com (scribd.com) (scribd.com) (scribd.com) and cokebusters.com. The timeframes are 1–2 days per heater, about 0.7 kg/cm² ΔP per 100 ft as a guide, and about 6 h to 1–3 days in total. The emissions are CO–CO₂–H₂.

Pigging performance is drawn from cokebusters.com and heatflux.com (heatflux.com) (heatflux.com) (heatflux.com). The removal is nearly 100%. The time is 36 h and 24 h against 96+ h, or 18 h per pass against about 96 h. Heat transfer performance is matched. Emissions are negligible. Operator time is saved. The sources also note the lost pigs. cokebusters.com notes the limitations of in‑line spalling.

All figures and procedures come from these engineering publications and field evaluations.