Project Portfolio

Beta Pramesti Asia projects: Kendal Industrial Park WWTP 16,200 m³/day, desalination plants, SPAM, power-plant water systems and industrial wastewater.

Updated

PT Beta Pramesti Asia’s project portfolio covers industrial-estate wastewater treatment, desalination plants, drinking water supply (SPAM) and water and wastewater systems for power plants and industry in Indonesia and Malaysia. Our latest project is the Kendal Industrial Park Phase 1B WWTP. Stage 1 has a capacity of 16,200 m³/day and uses the activated-sludge process. Construction runs 2025-2026 and start-up is in 2026.

Project list: client, location, capacity, process, year

This table is built from the reference data we have already published. A dash means the item is not stated in our reference record. For WWTP contracting, see industrial and industrial-estate WWTP contractor. Technology references are in wastewater, reverse osmosis and ultrafiltration.

ProjectClientLocationCapacitySystem/processYearScope
Kendal Industrial Park Phase 1B WWTP, Stage 1PT Kawasan Industri KendalKendal, Central Java16,200 m³/dayActivated-sludge WWTP with coagulation-flocculation, clarifiers and polishingConstruction 2025-2026, start-up 2026Design, civil, MEP, maintenance chemicals
Desalination Plant BatuputihPT Dua Samudera PerkasaBatuputih, Bombana, Southeast Sulawesi20 m³/hDesalination plant2022—
SPAM Kali AngkePT PP (Persero) Tbk.Kali Angke, Tangerang Selatan220 L/sDrinking water supply system (SPAM)2020—
PLTU Sulsel Barru II 100 MWPT PLN Nusantara PowerBarru, South SulawesiDesalination 2×25 m³/h; demin 2×12.5 m³/hDesalination and demin plant2019—
PLTU IndramayuPT Pembangkitan Jawa-Bali UBJOMIndramayu2×60 m³/h—2018—
PLTU NiasPT Pembangunan Perumahan (Persero)Nias——2016—
PLTU Anggrek 2×25 MWPT Rekadaya Elektrika / PT PLNNorth GorontaloDesalination WTP 2×39 m³/h; WWTP 720 m³/day; electrochlorination 2×20 kg/h; mixed bed 2×12.5 m³/hDesalination WTP, WWTP, electrochlorination, mixed bed2014—
Gajah TunggalPT Gajah Tunggal, TbkTangerang——2014—
CWCOBiosystems Group Consortium (CWCO)Bali1×1,000 m³/day—2012—
SamurEnersave Process Sdn BhdSabah Ammonia Urea (Samur), Malaysia——2012—
Ancol ProjectPT Jaya Teknik IndonesiaAncol, Jakarta5,000 m³/day—2010—
Bimoli Tanjung Priok SWROPT Salim Ivomas PratamaTanjung Priok, Jakarta1,000 m³/daySWRO2010—
WWTP 3 APICAL KRNPT Kutai Refinery NusantaraBalikpapan840 m³/dayWWTP——
STP Central Plaza LampungPT Sekala Braha SemestaLampung100 m³/daySewage treatment plant (STP)——

Project photos

Aerial view of the Kendal Industrial Park Phase 1B WWTP: aeration tanks, clarifiers and utility buildings
Kendal Industrial Park Phase 1B WWTP, Stage 1
Activated-sludge WWTP
Location: Kendal, Central Java
Year: construction 2025-2026
Capacity: 16,200 m³/day
Client: PT Kawasan Industri Kendal
PT Dua Samudera Perkasa - Desalination Plant
Portfolio Image 11 PT Dua Samudera Perkasa
Desalination Plant
Location: Batuputih, Bombana, Sulawesi Tenggara
Year: 2022
Capacity: Desalination Plant 20 m3/hour
Client: PT Dua Samudera Perkasa
PT PP (Persero) Tbk. - SPAM Kali Angke
Portfolio Image 10 Kali Angke PP
SPAM Kali Angke
Location: Kali Angke, Tangerang Selatan
Year: 2020
Capacity: 220 liter/detik
Client: PT. PP (Persero) Tbk.
PT PLN Nusantara Power - PLTU Sulsel Barru II 100 MW
Portfolio-Image-12-PLTU-Barru-II
PLTU Sulsel Barru II 100 MW
Location: Barru, Sulawesi Selatan
Year: 2019
Capacity: Desalination Plant 2×25 m3/H, Demin Plant 2×12.5 m3/H
Client: PT PLN Nusantara Power
PT Pembangkitan Jawa-Bali UBJOM - PLTU Indramayu
Portfolio-Image-2-PLTU-Indramayu (1)
PLTU Indramayu
Location: PLTU Indramayu, Indramayu
Year: 23 April 2018
Capacity: 2 x 60 m3/hour
Client: PT Pembangkitan Jawa-Bali UBJOM
PT Pembangunan Perumahan (Persero) - PLTU Nias
Portfolio-Image-7-PLTU-Nias
PLTU Nias
Location: PLTU Nias, Nias
Year: March 2016
Client: PT Pembangunan Perumahan (Persero)
PT Rekadaya Elektrika / PT PLN - PLTU Anggrek 2×25 MW
Portfolio-Image-3-Gorontalo
PLTU Anggrek 2×25 MW
Location: PLTU Anggrek, Gorontalo Utara
Year: 2014
Capacity: WTP Desalination 2×39 m3/h, WWTP 720 m3/day, Electrochlorination 2×20 kg/h, Mixed Bed 2×12.5 m3/h
Client: PT Rekadaya Elektrika / PT PLN
PT Gajah Tunggal, Tbk - Gajah Tunggal
Portfolio-Image-5-Gajah-Tunggal (1)
Gajah Tunggal
Location: Tangerang
Year: 2014
Client: PT Gajah Tunggal, Tbk
Biosystems Group Consortium - CWCO
401875_4499303610591_1777224032_n
CWCO
Location: Bali
Year: 2012
Capacity: 1 x 1000 m3/day
Client: Biosystems Group Consortium (CWCO)
Enersave Process Sdn Bhd - Samur
Portfolio-Image-6-Samur
Samur
Location: Sabah Ammonia Urea (Samur) - Malaysia
Year: 2012
Client: Enersave Process Sdn Bhd
PT Jaya Teknik Indonesia - Ancol Project
Portfolio-Image-1-Ancol-Project
Ancol Project
Location: Ancol, Jakarta
Year: 2010
Capacity: 5000 m3/day
Client: PT Jaya Teknik Indonesia
PT. Salim Ivomas Pratama - Bimoli Tanjung Priok SWRO
Portfolio-Image-12-Bimoli
Bimoli Tanjung Priok SWRO
Location: Tanjung Priok, Jakarta
Year: 2010
Capacity: 1000 m3/day
Client: PT. Salim Ivomas Pratama