WhatsApp

Information

Kendal Industrial Park Phase 1B WWTP (Stage 1: 16,200 m³/day)

Industrial-estate WWTP contractor: new Phase 1B WWTP for PT Kawasan Industri Kendal, Stage 1 16,200 m³/day, activated sludge, by Beta Pramesti Asia.

Updated

Aerial view of the whole Kendal Industrial Park Phase 1B WWTP: basins, aeration tanks, clarifier and utility buildings
The Kendal Industrial Park Phase 1B WWTP from the air.
16,200 m³/dayStage 1 capacity
Activated sludgeBiological process
2026Start of operation

PT Beta Pramesti Asia, an industrial-estate wastewater treatment plant contractor, is designing and building the new Phase 1B wastewater treatment plant (WWTP) for PT Kawasan Industri Kendal (Kendal Industrial Park) in Central Java, Indonesia. Stage 1 capacity is 16,200 m³/day. The plant uses the activated-sludge process with coagulation-flocculation, primary and secondary clarification, and polishing. Our scope covers design, civil works, mechanical-electrical-process (MEP) work and maintenance chemicals. Construction ran 2025-2026 and the plant started operating in 2026.

This is our latest large-scale WWTP reference, built for an industrial estate.

Project summary

ItemDetail
ClientPT Kawasan Industri Kendal (Kendal Industrial Park)
LocationKendal, Central Java, Indonesia
SectorIndustrial estate
PhasePhase 1B, Stage 1 — design and construction of the new WWTP
CapacityStage 1: 16,200 m³/day
ProcessActivated sludge, with physical-chemical treatment ahead of and polishing after the biological stage
Beta Pramesti Asia scopeDesign, civil works, mechanical-electrical-process (MEP) and maintenance chemicals
ScheduleAwarded mid-2025; piling from September 2025; construction 2025-2026; bacterial seeding and biological start-up in the second half of 2026
StatusOperating; start-up in 2026

How is the Kendal WWTP process train arranged?

The train below follows the equipment installed on the project. Each step has one clear job, so performance can be checked unit by unit during start-up.

No.StepMain equipmentPurpose
1Buffer and equalisationBuffer/equalisation ponds with submersible mixers and lift pumpsEven out flow and load from many tenants before treatment
2Coagulation and flocculationCoagulation and flocculation tanks with chemical dosingAgglomerate colloidal solids and part of the organic load
3Primary clarificationPrimary clarifier with chain-and-flight scrapers and scum skimmerSettle the floc and remove surface scum and oil
4Aeration (activated sludge)Aeration tanks with fine-bubble diffusers and variable-speed screw blowersBacteria break down dissolved organic load with an adjustable oxygen supply
5Secondary clarificationTwo secondary clarifiers with return (RAS) and waste (WAS) sludge pumpingSeparate biomass from treated water and return part of the sludge to aeration
6PolishingPolishing clarifier with tube settlersCapture remaining fine solids before discharge
7Sludge treatmentScrew press with automatic polymer preparationReduce sludge water content before final handling
8Control and utilitiesRedundant PLC with SCADA; online flow, turbidity and organic-load instruments; standby generatorMonitor the process continuously and keep it running through power interruptions

Photos of the Kendal Industrial Park WWTP

Aerial view of the aeration tanks and clarifiers at the Kendal Industrial Park WWTP with aeration running
Aeration tanks and clarifiers from the air, with aeration running.
Aerial view of the basins and process tanks at the Kendal Industrial Park WWTP
Basins and process tanks from the air.
Top-down view of the whole Kendal Industrial Park WWTP site
The whole WWTP site, seen from above.
Activated-sludge aeration tank in operation at the Kendal Industrial Park WWTP
Activated-sludge aeration tank.
Concrete channel and utility buildings at the Kendal Industrial Park WWTP
Concrete channel and utility buildings.
PT Beta Pramesti Asia staff on the clarifier bridge at the Kendal Industrial Park WWTP
Beta Pramesti Asia staff on the clarifier bridge.
PT Beta Pramesti Asia staff taking a sample at the aeration tank of the Kendal WWTP
Sampling at the aeration tank.
Primary clarifier at the Kendal Industrial Park WWTP
Primary clarifier.
Chemical dosing room at the Kendal WWTP with solution tanks and dosing pumps
Chemical dosing room.
Screw blowers in the blower room of the Kendal Industrial Park WWTP
Screw blowers for aeration.
Standby generator at the Kendal Industrial Park WWTP
Standby generator.
PT Beta Pramesti Asia operator watching the SCADA screens in the Kendal WWTP control room
Control room with SCADA.
PT Beta Pramesti Asia technician checking an electrical panel at the Kendal WWTP
Checking the electrical panel.
Water sample analysis in the laboratory of the Kendal Industrial Park WWTP
Sample analysis in the WWTP laboratory.
PT Beta Pramesti Asia staff at a clarifier of the Kendal Industrial Park WWTP
Beta Pramesti Asia staff at the clarifier.
Construction of the Kendal Industrial Park Phase 1B WWTP by PT Beta Pramesti Asia
During construction.

Why activated sludge rather than MBBR or MBR?

The Kendal WWTP is a conventional activated-sludge plant with clarifiers. It is not an MBBR (moving-bed biofilm) plant and not an MBR (membrane) plant. For a large central industrial-estate WWTP with land available, activated sludge with large equalisation, physical-chemical treatment upstream and polishing downstream is a common train to evaluate. The MBBR vs MBR vs activated sludge article explains how the three processes differ.

What does an industrial-estate WWTP contractor do?

An industrial-estate WWTP contractor builds one plant for many tenants. That is wider work than a single-factory plant: the design basis comes from the combined tenant wastewater, equalisation must be large enough to absorb load and pH from many sources, and the estate needs pretreatment rules and sampling points for its tenants. On the Kendal project our scope covers design, civil works, MEP and maintenance chemicals.

Industrial-estate WWTP needWhat the contractor delivers
Mixed influent from many tenantsFlow and load characterisation per source as the design basis, then process selection from that data
Load and pH shift when new tenants arriveBuffer/equalisation ponds with mixers and lift pumps; capacity built in stages as the estate fills
Many dischargers, one operatorPretreatment rules and sampling points for tenants; online flow, turbidity and organic-load monitoring; redundant PLC with SCADA; standby generator
Biological start-up for the whole estateBacterial seeding and stepwise load increase while tracking DO, pH, MLSS and settling
Maintenance after start-upMaintenance chemical programme for coagulation-flocculation and sludge-dewatering polymer

What is specific to an industrial-estate WWTP?

  • Many wastewater sources. Tenants discharge different loads, pH and schedules, so equalisation and online monitoring come first.
  • Influent acceptance limits. The estate operator needs pretreatment rules for tenants so toxic or oily discharges do not upset the bacteria.
  • Long-term operation. Control redundancy, a standby generator and a maintenance chemical programme keep the plant running when load rises or power fails.
  • Staged biological start-up. Bacteria are seeded and load is raised step by step while DO, pH, MLSS and settling are tracked; see WWTP bacteria seeding service.

Kendal WWTP project FAQ

What is the capacity of the Kendal Industrial Park Phase 1B WWTP?

Stage 1 capacity is 16,200 m³ per day. This is the first-stage capacity within the Phase 1B works.

Which process does the Kendal WWTP use?

The biological process is activated sludge with fine-bubble aeration, two secondary clarifiers, and return and waste sludge pumping. Equalisation, coagulation-flocculation and a primary clarifier come before the biology; a polishing clarifier with tube settlers comes after it. The plant is neither MBBR nor MBR.

What is Beta Pramesti Asia’s scope on this project?

Design, civil works, mechanical-electrical-process (MEP) work and maintenance chemicals.

When did the Kendal WWTP start up?

The Kendal WWTP is operating. Construction ran 2025-2026, with bacterial seeding and biological start-up in the second half of 2026.

We operate an industrial estate. How do we start a WWTP discussion?

Send average and peak flow, a list of tenant types, influent analyses, the effluent target and Technical Approval, available land and expansion plans through the contact page. Our team will map missing data before defining the scope.